A big step towards getting back to the Loop!
It might have been a wet and soggy morning, but there was plenty to smile about today. Why? We have commenced an exciting project to bring the railway back to the Loop Platform and Magnus’s.
The project will see the overhaul and heavy maintenance of four of our bridges. The total cost of the project is approximately £300,000. Of this, £250,000 has been secured from The National Lottery Heritage Fund Northern Ireland. We have also benefited from additional support from Newry, Mourne and Down District Council, and are also using some of our own reserves.
As many will know, the flooding in late 2023 accelerated the deterioration of our bridges, particularly along the south line. These structures remain safe to cross. However, passenger trains have not operated over the bridges spanning the Plank Drain since the floods. This project is therefore essential to securing their long-term future and restoring this important section of our railway.
Among the structures is an original riveted bridge dating from the days of the old Belfast and County Down Railway, an important piece of our railway heritage which, if we act now, can be preserved for future generations.
AtkinsRéalis appointed as bridge project management team
We have appointed AtkinsRéalis as our project management team. They are already well established in Northern Ireland’s rail industry, having worked with Translink on the assessment, repair and maintenance of its railway infrastructure. A key project they have worked on was supporting the delivery of Belfast Grand Central Station. As such, they are no strangers when it comes to these sorts of structures.
Initial site visit
As part of the initial site visit, Judith Travers and Simran Das from AtkinsRéalis joined DCDR Infrastructure Manager David Crone and Chris Johnson to see the bridges for themselves and get a better understanding of the work ahead.
Of course, this is still a substantial undertaking, and we need your support to help make it happen. If you would like to play a part, visit our donations page and make a contribution. Let’s get back to the Loop in time to celebrate the 40th anniversary of our little railway reaching the Loop Platform in 1987.
We hope to see work commencing in the new year. Wish us luck!